Forum / News / August Bank Holiday Kings Cross closure.
Reply Subscribe Start new thread Syndicated Feed (RSS)
Displaying 1 to 2 of 2 | Previous 1 Next |
Author | Message | ||
---|---|---|---|
8001F
Posts: 5528 Location: |
The main work is on Kings Cross's throat and the video shows 40 PSRMs at the entrance to the Gas Works Tunnels when the entire scheme is completed. A worksite is already established by the redundant easterly tunnel. NR 04.06.19 |
||
Back to top | View user profile Contact this member | ||
CTAYLOR
Posts: 533 Location: |
A long Press Release but the crux is that no trains will run between Kings Cross and Peterborough on the 24/25th August. Work is also going on at Newark which will affect trains on the 26th. The work at Newark is to renew the crossing. |
||
Back to top | View user profile Contact this member |